CentrePort Station Improvements and Double Tracking, Fort Worth, TX.
2CMD was responsible for improvement of 7,000 feet of track with wood ties, ballast and rail, as well as 90,000 cubic yards of excavation and 22,000 square feet of steel sheet piles. The project also included constructing two bridges with 54-inch diameter drilled piers supporting 84 pre-stressed concrete box beams with 1,000 square yards of 6-inch concrete platform. 2CMD’s duties included providing an on-site construction contract administrator, on-call structural specialty observer and on-call QA/QC specialty observer over a 2-year period. CM